US Data Center Buildout Hitting A Major Bottleneck. Nvidia's primary market share is not in the United States, it is China!!
Jensen Huang assists Satanic CPC China to destroy America.
About half of the US data centers planned to open in 2026 are expected to be delayed or canceled, according to analysts at Sightline Climate. Of the 12 gigawatts of data center capacity announced for this year, only a third is actually under construction. The problem is not money or ambition but electrical components. Transformers, switchgear, and batteries make up less than 10% of data center construction costs but are impossible to build without. US manufacturing cannot meet demand so builders have been sourcing from China, Canada, Mexico, and South Korea. Transformer delivery times have stretched to as long as five years. US imports of high-power transformers from China jumped from fewer than 1,500 in all of 2022 to more than 8,000 in the first ten months of 2025 alone.